FAST! Architecture: Factory Built Large Format Pre-Fabrication

Project facts

Location: Truginina, VIC
Client:      Stockland
Stages:     Schematic – Completion
Area:        474 m2
Budget:    $6 million
Team:       TBLD, A2M, Pre-Built
Date:         2020 – 2022

Competition winning entry to create a new community building for Mt Atkinson Estate.

Scope

  • TANDEM were chosen through design competition to design a new vision centre for Stockland
  • This building is mixed use, housing a cafe, sales centre, offices

Objectives

  • Create a landmark for the new town centre
  • Create a temporary administrative and sales centre for new town centre

Challenges

  • To deliver a high quality built form within a short timeframe, required fabrication to commence in advances of the planning permit being granted
  • A fast track design program, coupled with an off site, factory built strategy was required to meet this very short building program

Outcomes

  • Our competition response involved the direct metaphor of child’s play, using ‘jenga’ building blocks to express the joy and excitement of new building
  • These ‘jenga’ blocks were designed to be built off site, transported to site and installed by crane; the design expresses this process
  • This approach will realise a short site program, along with factory controlled building tolerances creating lower tolerances, safer working conditions and less waste
  • The assembly line approach leads to higher environmental performance of the building envelope, coupled with a superior finish than conventional building approach.